The pay-off rack is a working tool. The existing cable pay-off rack has a slow take-up speed and does not restrict the wire wound on the reel, which affects the pay-off and take-up. The new cable pay-off frame includes a frame body, a reel with a rolling device on the frame body, and a winding handle for rolling the reel. An acceleration transmission mechanism is installed between the winding handle and the reel, and a guide frame is installed on the frame body. , the guide frame is held by the elastic element to approach the reel.
When the new cable pay-off rack passes through the rolling handle to take up the wire, the reel rolls quickly to achieve fast take-up through the acceleration transmission mechanism; when taking up and paying off the wire, the guide frame can hold the wire. Therefore, whether it is pay-off or take-up, the rolling of the reel and the line are constrained. Therefore, the reel will not roll too fast, and the line will not be reversely wound on the reel during pay-off to affect the use. The wire will not be wound on the frame body, nor will it be wound loosely and irregularly on the reel, but will be wound on the reel in a regular, layer-by-layer manner, which is convenient for later use.
After the pay-off frame is produced, the installation of each component is also important. The following introduces the installation and precautions.
One: It is necessary to clarify the type and type of the cable pay-off rack to be installed, to know the installation process, to be able to draw up the installation process specification, to decompose the installation process of the cable pay-off rack, and to list the required material table.
Two: Check whether all the low parts of the cable pay-off rack are complete, and check for defects, so as to avoid finding that the low parts of the installation are unqualified and the process is blocked, and if the low parts of the first installation are unqualified, disassemble it and return it. It will cause damage to other low parts and waste human and material resources.
Three: Check whether the tools used for the cable release rack of the device are complete, and whether the accessories and auxiliary materials are complete.
Four: After the cable pay-off rack is installed, it is necessary to follow the corresponding installation process.
Five: After the installation reaches a certain level, the quality inspection of the cable release frame should be carried out to see if there are any faults, so as to avoid problems and poor judgment.
Six: After the whole machine of the pay-off rack is installed, it should be put into trial operation immediately, and the problems should be recorded clearly and expressed for improvement.